Applied Digital announced on Monday, November 23, 2026, that it has signed a new 18-year lease with a tier-one, investment-grade hyperscaler for 150 megawatts of critical IT capacity, in a deal the company expects to generate approximately 5.4 billion dollars in contracted revenue over its base term.
The tenant was not named. If all renewal options are exercised, the agreement could run for a total of 33 years and be worth approximately 12.7 billion dollars. Applied Digital said the lease carries improved commercial terms over its prior agreements, including higher pricing, and that the longer 18-year duration gives the company greater long-term revenue visibility.
With this addition, Applied Digital says its total contracted base-term lease revenue now exceeds 41 billion dollars, or approximately 100 billion dollars if all renewal options across its portfolio are exercised. Its portfolio now stands at more than 1.6 gigawatts of total contracted critical IT load and 2.2 gigawatts of grid-connected peak load. About 75 percent of its contracted base-term lease revenue is now attributable to investment-grade customers, a figure the company cited as evidence of the credit quality of its customer base.
The deal follows a pattern of large, long leases for the Dallas-based builder. Reuters noted that it comes after a 15-year, 210-megawatt lease worth about 5.2 billion dollars that Applied Digital signed in June at its Delta Forge 2 site, underscoring how hyperscalers are locking up purpose-built AI capacity years ahead of delivery rather than waiting for space to come to market.
Delivery of the new capacity is expected to begin in the first half of calendar 2028, subject to development milestones, utility arrangements, and regulatory approvals. That timeline is typical for large AI campuses, where power interconnection and construction schedules, rather than server supply, now set the pace.
Financing remains the other half of the story. Chief Financial Officer Saidal Mohmand said the company plans to finance the build through its established structure, starting with equity already funded from its balance sheet and its 5 billion dollar programmatic equity partnership with Macquarie Asset Management, followed by project financing supported by the long-term lease. He said the company expects to complete the remaining project finance for Delta Forge 1 and Polaris Forge 3 in the first quarter of 2027, followed by Delta Forge 2 in the second quarter of 2027.
Chairman and Chief Executive Officer Wes Cummins said securing another large-scale, long-term lease with a tier-one investment-grade hyperscaler reinforces the strength of the company's customer relationships and the quality of its contracted revenue, adding that its focus remains on executing with speed, discipline, and consistency.
For enterprise IT leaders, the significance is less about one landlord's backlog than about what the terms reveal. Hyperscalers are committing to 18-year base terms at higher pricing to secure powered, liquid-cooled capacity for AI training and inference, and they are signing well before delivery. That locks in supply for the largest buyers while pushing smaller enterprises toward colocation providers, regional builds, or waiting lists. Applied Digital, which designs and operates large AI factory campuses with advanced liquid cooling and connectivity for high-performance computing workloads, is betting that long contracts with creditworthy tenants will keep capital flowing even as power and financing costs stay in focus.